Westminster City School is part of the BSF Programme with approximately £13 million being spent on new buildings and the refurbishment of existing buildings to provide the school with the facilities to match its aspirations.
Phase 1: July 2009-August 2009
Construction of new building including basement, sports hall, activity hall. New music, drama and ICT specialist, administration and sixth form areas. Refurbishment Assembly hall, Learning Resource Centre (LRC) and maths rooms.
Phase 2: September 2009-December 2009
Music and sports block, English and administration areas.
Phase 3: January 2010-May 2010
First floor general classrooms
Second floor geography rooms
Phase 4: June 2010-August 2010
Completion of Multi-Use Games Area (MUGA).